Habeeb Shittu and the Engineering Behind Port Electrification

Written by
Read time
6 min
Published
Filed under
Add to Preferred Sources
For ports turning investment into working assets, the decisive work continues after the cable reaches the ship

As ports invest in cleaner equipment, the harder task is coordinating the electricity supply, storage and controls needed to keep cargo moving.

A ship connects to shore power and switches off its auxiliary diesel generators. For a port pursuing cleaner air, that is a visible milestone. For the electrical network serving the terminal, it is the start of a demanding operating task: supplying the vessel while cranes, refrigerated containers and vehicle chargers continue drawing power around it.

The challenge becomes sharper when electrification projects share the same limited supply. A terminal may have enough capacity for each new asset considered separately, yet face a constraint when those assets operate together. The timing of demand can matter as much as the equipment being purchased.

Habeeb Shittu’s work sits within this engineering problem. An electrical engineer whose background includes port power-system design at Moffatt & Nichol, he has also co-authored research examining how digital twins and intelligent controls could coordinate maritime energy infrastructure. That combination places his research in the context of a practical question facing terminal operators: how to electrify without creating new constraints on cargo operations.

Investment meets the limits of existing infrastructure

The scale of the transition is substantial. The U.S. Environmental Protection Agency’s Clean Ports Program awards page currently lists 51 projects worth nearly $3 billion across 24 states and territories. They include equipment purchases, shore power, solar generation and planning activities. That investment creates an engineering obligation: new assets must be supported by infrastructure capable of serving them.

Europe adds a regulatory timetable. Under FuelEU Maritime, covered passenger and container ships above 5,000 gross tonnage must use shore power or qualifying zero-emission alternatives at berth from 1 January 2030 in EU ports covered by Article 9 of the Alternative Fuels Infrastructure Regulation. Applicable exceptions remain, and the obligation extends from 2035 to other EU ports equipped with shore power. The timetable also matters to UK shipping businesses serving those destinations.

For international shipping operators, the practical consequence is a need to coordinate vessel capability with the facilities available at each destination. For ports, a connection point on the quay is only one component of that preparation.

Independent evidence of the infrastructure challenge comes from the Seattle Waterfront Clean Energy Strategy, developed with the Northwest Seaport Alliance and Seattle City Light. It forecasts a fourfold increase in port peak electricity demand by 2050 against a 2019 baseline. Eight port sites are expected to exceed total site capacity during the forecast period, while 10 of 16 utility distribution feeders serving key maritime facilities are expected to exceed capacity planning limits by 2040.

Seattle’s published assessment identifies $208 million to $457 million in port and utility distribution investment through 2050, in 2024 dollars. It also finds that upgrading existing infrastructure is currently the most cost-effective response to the constraints studied. That conclusion gives emerging energy technologies a practical role alongside conventional network investment.

Designing around simultaneous demand

Shittu’s professional background includes medium- and low-voltage distribution networks, substations and electrical systems serving maritime facilities. These disciplines underpin decisions that can be obscured by the visibility of a new charging unit or shore connection: how much load a feeder can carry, how equipment is protected, and how future expansion fits into the original design.

A useful illustration is a terminal where vessel connection coincides with a vehicle-charging period. The engineering question is whether the shared transformers and cables can support both demands while maintaining acceptable operating conditions. If they cannot, the options may include additional capacity, a revised charging schedule or a properly sized storage system. The right choice depends on the terminal’s operating schedule and electrical constraints.

The commercial implications follow directly. A charger that cannot deliver the required energy before a truck returns to service has limited operational value. An energy plan therefore needs to connect electrical limits with berth schedules, cargo commitments and equipment availability.

What storage can realistically contribute

Battery storage can help manage short periods of high demand. The U.S. Energy Information Administration identifies demand reduction and lower demand charges among its potential uses for commercial and industrial customers. Whether those benefits justify a port installation depends on its load profile, tariff and operating requirements.

A battery shifts energy through time; it does not create an unlimited supply. Its power rating determines how much demand it can support at once, while its usable energy capacity constrains how long it can provide that support. Recharging also requires available electricity. Where demand remains high for extended periods, storage alone may leave the underlying supply constraint unresolved.

Outage resilience requires additional design decisions. The U.S. Department of Energy describes microgrids that can operate with the utility grid or independently in an islanded mode. For a port, that capability requires appropriate controls, protection and energy resources. The loads supported and the duration of operation must be defined; installing solar panels and a battery does not by itself establish that an entire terminal can operate through an outage.

A research framework for coordinating port energy

Shittu and his co-authors address system coordination in their 2026 paper, Autonomous Energy Management Systems for Port and Maritime Electrical Infrastructure Using Digital-Twin-Driven Architectures, published in the International Journal of Advanced Multidisciplinary Research and Studies. The paper uses literature synthesis and conceptual architectural analysis to examine how modelling, data acquisition and control could be integrated.

A digital twin is a software representation maintained using information from the physical system. In the proposed approach, it could help evaluate operating choices before control actions are applied. For example, an energy manager could examine whether delaying a flexible charging load would leave more capacity available for a vessel connection.

This is a proposed architecture, rather than evidence of a commissioned autonomous port system. Its practical value would need to be established through validation, testing and operational results. The paper itself identifies challenges involving model standardisation, autonomous-decision validation, cybersecurity and institutional readiness.

Those qualifications sharpen the research question. A model must represent actual equipment constraints closely enough to inform decisions. Operators also need clear authority to intervene when schedules change, data become unreliable or an automated recommendation conflicts with safe operation.

Security belongs in the control design

Coordinating more equipment through digital controls introduces another dependency: trustworthy communications. An incorrect signal or unauthorised command can affect physical equipment, making security part of the operating design.

The U.S. National Institute of Standards and Technology’s Guide to Operational Technology Security addresses security alongside the performance, reliability and safety requirements of industrial systems. Network segmentation, controlled remote access and monitoring are relevant considerations when connecting energy-management platforms to terminal equipment.

For ports adopting intelligent energy controls, the practical questions include who may change operating settings, how access is recorded, and how the facility responds when communications fail. These requirements should be specified before a control platform is integrated into essential operations.

The test is reliable operation

The strongest case for port energy technology is an operational one. Can vessels connect when scheduled? Can vehicles finish charging before their next shift? Can the system remain within electrical limits while meeting cargo commitments? Answering those questions requires cooperation between utilities, terminal operators, equipment suppliers and electrical designers.

Shittu’s design background and published research connect to that task through their focus on the infrastructure and coordination supporting electrification. The next measure of any proposed architecture is evidence from testing and deployment: reliable operation, manageable costs and decisions that operators can understand and control.

For ports turning investment into working assets, the decisive work continues after the cable reaches the ship. It lies in ensuring that the network behind it can meet the demands of a busy terminal, throughout the operating day.

Never miss a storyThe TechBullion Weekly newsletter and your preferred channels.Subscribe